dcondo Hatyai

Expected completion Date : September 2024
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Pile-driving work all completed
    Floor structual work is completed for Tower A
    Floor structual work is completed for Tower B
  • Systems installation
    Tower A : Installation of eletric work is completed on Floor 7 ,
    Installation of pumbling systems underway on Floor7 ,
    Installation of A/C systems underway on Floor 4
    Tower B : Installation of eletric work is completed on Floor 7 ,
    Installation of pumbling systems underway on Floor7 ,
    Installation of A/C systems underway on Floor 4
  • Architectural Work
    Tower A : Wall construction is completed on Floor 7
    Tower B : Wall construction is completed on Floor 6