PROJECT PROGRESS
![](../../uploads/projectcms_asset/condo-dcondo-reef-logo-en.png)
dcondo reef Phuket
Expected completion Date : September 2024
- The environmental impact assessment has been approved.
- A construction permit has already been issued.
-
Structural Work
Pile-driving work all completed
Structual work is completed on Deck Level for Tower A
Structual work is completed on Deck Level for Tower B
Structual work is completed on Deck Level for Tower C -
Systems installation
Tower A : Installation of eletric work is completed on Floor 7 ,
Installation of pumbling systems underway on Floor7 ,
Installation of A/C systems underway on Floor 5
Tower B : Installation of eletric work is completed on Floor 8 ,
Installation of pumbling systems underway on Floor7 ,
Installation of A/C systems underway on Floor 6
TOWER C Installation of eletric work is completed on Floor 8 ,
Installation of pumbling systems underway on Floor7 ,
Installation of A/C systems underway on Floor 6 -
Architectural Work
Tower A : Wall construction is completed on Floor 8
Tower B : Wall construction is completed on Floor 8
Tower C : Wall construction is completed on Floor 8