Date: June 2024
Date: June 2024
Date: June 2024
Date: June 2024
Date: May 2024
Date: May 2024
Date: May 2024
Date: May 2024
Date: April 2024
Date: April 2024
Date: April 2024
Date: April 2024
Date: March 2024
Date: March 2024
Date: March 2024
Date: March 2024

dcondo hype rangsit

Expected completion Date : September 2024
  • The environmental impact assessment has been approved.
  • A construction permit has already been issued.
  • Structural Work
    Pile-driving work is 100%
    Structual work is completed for Tower A
    Structual work is completed for Tower B
  • Systems installation
    Tower A : Installation of eletric systems underway is 100% on Floor 8 ,
    Installation of pumbling systems underway on Floor 8
    Tower B : Installation of eletric systems underway is 100% on Floor 8 ,
    Installation of pumbling systems underway on Floor 8
  • Architectural Work
    Tower A : Wall construction is completed on Floor 8
    Tower B : Wall construction is completed on Floor 8