PROJECT PROGRESS
![](../../uploads/projectcms_asset/thebase-bukit-condo-logo.png)
THE BASE Bukit Phuket
Expected completion Date : August 2025
- The environmental impact assessment has been approved.
- A construction permit has already been issued.
-
Structural Work
Pile-driving work and Foundation work is 100%
Installation of underground water tanks completed for Tower A
Installation of underground parking completed for Tower B
Structual work is completed for Tower C -
Systems installation
-
Architectural Work